Project case study
Rocklea Palms Central Facility Refurbishment
Client
Location
Focus
Status
Project Overview
Byblos Constructions was engaged to deliver a major refurbishment of the Rocklea Palms Central Facilities, targeting critical operational infrastructure within an active village environment.
The project focused on upgrading essential areas including the kitchen, coolrooms and wet areas, as well as improving overall building functionality, compliance, and long-term performance. Works were undertaken within a live operating facility, requiring careful planning and coordination to minimise disruption to village operations.
Completed (June 2021 – March 2022)
Scope of Works
- Full internal and external refurbishment of central facilities
- Refurbishment of kitchen, coolrooms and wet areas
- Removal and safe disposal of asbestos-containing materials
- Structural modifications, including wall removals
- Complete replacement of flooring throughout
- Painting and surface finishes upgrades
- Tiling works to wet areas
- Electrical and plumbing system upgrades
- Full re-roofing of the facility
Key Challenges
- Delivery within a live operational village environment
- Managing COVID-19 impacts, including:
- Workforce mobilisation restrictions
- Supply chain delays and material availability
- Programme uncertainty and scheduling disruption
- Coordinating multiple trades within confined operational areas
- Maintaining safety and compliance during intrusive works
Outcomes
The project resulted in the complete transformation of the kitchen mess and central facilities, significantly improving functionality, reliability, and amenity for end users.
Key achievements include:
- Delivered on time and within budget
- Exceeded client quality expectations
- Successfully completed all works with minimal operational disruption
- Upgraded facilities to meet modern standards and performance requirements